PerupetroBenefits
March 15, 2010
Ethic Code News Contact Us Espaņol Canon Site Map Home
Search:
Our CompanyNew Explo OpportunitiesLegal FrameworkNegotiations and ContractsUpstreamStatisticsLibraryContacts

Virtual Data Room
Contact Us
Camisea Project

Ministerio de Energía y Minas

ProInversión

Miniesterio de Economía y Finanzas

Estado Peruano

Prom Perú

space.gif (43 bytes)

Camisea Project

Project Progress

back to menu >>>

LICENSE CONTRACT FOR THE EXPLOITATION OF CAMISEA FIELDS

To execute the Exploitation Initial Project, the Contractor (Consortium headed by PLUSPETROL) established two different geographical areas for the works execution. The Upstream Area comprising all the works to be performed in the Camisea Area and the Downstream Area comprising all the works to be performed in the Pisco Area.

The main works to be performed in the Upstream Area are:

  • Well Drilling
  • Natural Gas Gathering and Reinjection System (Flow Lines)
  • Natural Gas Liquids Separation Plant
  • Gas Compression Plant for Reinjection and Transportation

Main works in the Downstream Area are:

  • Natural Gas Liquids Fractionation Plant
  • Condensates Topping Plant
  • Products Storage and Loading System

Within the Upstream Area, the Contractor has included a seismic acquisition project to improve the understanding of the gas fields, which is not a contractual obligation for the Contractor.

The EIA for Camisea works was approved on December 17 2001, as consequence execution of works began since that date.

In relation to the EIA for Pisco works, on April 4, 2003 the DGAA (General Directorate of Environmental Affairs) approved it, subject to the fulfillment of some obligations and commitments. This approval allowed to start works of onshore components of Fractionation Plant. On July 11, 2003 the DGAA gave definitive approval to the EIA of NGL Fractionation Plant Project, Loading Facilities and Alternative Submarine Piping in Loberia Beach, Pisco, thus allowing to start works of the offshore components of the Project.

Work Execution Plan

Contractor is developing a “segmented-hiring and focused-supervision” Work Execution Plan. This method is due to the need of accelerating the execution of the project works in order to comply with the terms committed, optimizing the project progress with the specific and coordinated handle of studies, approvals and critical acquisitions, adapting them to the climate conditions, logistic facilities and financial availability.

Contractor, with the support of a supervisory enterprise (Paragon Engineering Services) performed the organization, administration and supervision of the project works execution.

For the specific works execution, these were segmented in different contracts: Contracts for studies, design, main equipment manufacturing, critical equipment acquisition, civil construction, installation and mounting, etc.

Locación San Martín 1: Equipo de Perforación PARKER 228EXPLOITATION PROJECT ACTIVITIES AND PROGRESS

Well Drilling

Parker Drilling Co. was in charge of the initial project wells drilling. From July 2002 to June 2003 wells San Martin 1001, San Martin 1004, San Martin 1002 and san Martin 1003 were successfully drilled in San Martin 1 platform. At the same time production tests for San Martin 1001, 1004 and 1002 were executed. During August 2003, workover of San Martin 1X finished.

During September 2003 to February 2004, drilling of San Martin 1005, San Martin 1006 and San Martin 3X-ST1in San Martin 3 platform, was executed.

On April 5, 2004 the project started up with the opening of SM 1002 well and the increase of pressure in San Martín 1 cluster.

Flow Lines Building

These works were executed by SADE and JJC General Contractors. Starting in March 2002 in the Malvinas to San martin 1 section and ending in December 2002.

Erosion remediation and control works in the Flowlines route were performed within October 2002 ans April 2004.

Construction of the Separation Plant and Facilities in Malvinas

In March 2002 works of Contract C-2 in charge of Graña y Montero were completed including the building of fuel storage tanks, water tank, two river docks, warehouses, deposits and roads.

In April 2003, Graña y Montero finished works corresponding to C-1 Contract, consisting of civil works and foundations for installing separation and compression plants, as well as the building of a landing strip, mechanical workshops and main camp.

On November 2002, works corresponding to Contract C3 consisting in the building of control room for Separation Plant and Workshop and Warehouse buildings. During June 2003 finished works of Contract C3.

On the other side, abroad, different engineering and supply companies are executing manufacturing works of installation and critical equipment corresponding to the Separation Plant, Compressors and Facilities which were finished in November 2002. In December 2002, BBC Pacific and Challenger vessels arrived to Iquitos harbor transporting Compressors and Separation Plant equipment . In February 2003 reception of equipments and the components of Separation and Compression Plant was completed.

Plant mounting and balance works were charged to the consortium integrated by Sade, JJC and Latintecna S.A. Assembling of Separation and Compression Plant began at the end of January 2003, and finished during the first week of April 2004.

On April 9, 2004 was the start up of the Separation Plant of Malvinas, when Gas from San Martin 1 Platform, reached the Separation Plant.

On June 2, 2004 started the filling of the Camisea Pipeline to Lima, considering such date as the beginning of Commercial Extraction of Exploitation Contract of Camisea Fields – Block 88.

Building of Fractionation Plant and Facilities in Pisco

In April 2003, Consortium TECHINT/ Graña y Montero began land movement and conditioning corresponding to Contract EPC-2: Civil works and mounting of Fractionation Plant in a plot of land near Loberia beach, Pisco.

Main works and contracts for building of Onshore component of the Fractionation Plant are the following:

  • EP-F Construction of Fractionation and Topping Plant charged to HOWE BAKER.
  • EPC-D construction of Refrigerated and Atmospheric Tanks charge to CBI.
  • PEC-2 contract of civil works and mounting of Fractionation Plant charge to TECHINT/Graña Montero Consortium.

 

Up to May 2004 continue works for building Fractionation Plant of Loberia Beach – Pisco, reaching a progress of 90%.

Main Works corresponding to Offshore Component of Fractionation Plant are the following:

  • Construction of submarine lines for shipment of propane, butane, natural gasoline and diesel.
  • Construction of Loading Platform for shipment of products.

These works are being executed by consortium BELFI – COSAPI and began in October 2003, starting with the piles anchorage for the Loading Platform building

Up to the end of May 2004 a progress of 75% have been reached in the building of Offshore component.

CONCESSION CONTRACTS FOR THE TRANSPORT AND DISTRIBUTION OF THE CAMISEA GAS AND LIQUIDS

The Transportation and Distribution Project includes the construction of a Natural Gas and Natural Gas Liquids Pipeline Transportation System from the Camisea fields (South Jungle – Cuzco) up to the Central Coast of the country, having two main components:

One Natural Gas pipeline of approximately 710 km length, going from the Malvinas Gas Plant (Camisea) to the City Gate in Lurin – Lima.

One Natural Gas Liquids pipeline of approximately 540 km length, going from the Malvinas Gas Separation Plant (Camisea) to the Fractionation Plant and Terminal in Pisco.

The licensee (TGP Consortium – Transportadora de Gas del Perú) has developed a pipeline construction strategy according to geographical impediments, access availability and materials supply, dividing pipeline construction in three big working areas: Jungle Section, Mountain Section and Coast Section.

Transportation Project Activities and Progress

Up to March 2002, approval of the Environmental Impact Assessment of the Natural Gas and Natural Gas Liquids Transportation Systems has been obtained, as consequence the Licensee began with the project works.

During March 2002 construction works for camps in the jungle and mountain area, as well as plants clearing and roads opening in Malvinas, Kepashiato and Rumichaca.

Main activities of pre-building were also performed during 2002, including permits, topographic surveys and definition of pipeline route.

Up to April 2004, the process to obtain rights of way finished.

Concerning logistics for the project development, Contractor is performing transportation of tubing, equipment and necessary material for pipeline construction. These activities are being executed by river and by land, treating that the load be stored in the previously selected gathering points.

Progress reached in pipelines construction are the following:

  • During December 2003, finished jungle works of both ducts: execution of a total of 180 km of rights of way opening, trenching, pipe stringing, welding and back-filling of NGL Pipeline (14” pipe), and Gas Pipeline (32” pipe).
  • - During January 2004, finished mountain works of both ducts: execution of a total of: 340 km of rights of way opening, trenching, pipe stringing, welding and back-filling of NGL Pipeline (14” pipe) and gas pipeline (24” pipe).
  • During March 2004, finished works in the Coast: executing a total of 210 km of rights of way opening, 210 km of pipe stringing and welding of the gas pipeline (18” pipe).
  • In February 2004, works for NLG pipe stringing in the Coast finished , completing welding and back filling of 40 km. of 18” pipe.
  • Building works of the Pipeline from Camisea to the Coast finished in March 2004.
  • In April 2004 finished works for hydraulic tests of gas and liquid pipelines.
  • Continue building works of Pumping Stations and Pressure Control with a progress of 99%.
  • At the same time erosion remediation and control works continue along the Pipelines route.

Activities and Progress of the Gas Distribution Project in Lima and Callao

Transport and Distribution Project also includes the construction of the Natural Gas Distribution System in Lima and Callao, which is being executed by GNLC, enterprise of TRACTEBEL Group, selected by TGP Consortium as licensee of the Distribution System.

The mentioned Distribution System includes a tubing network for gas transportation from the city gate in Lurin up to the Terminal Station in Ventanilla. The system main duct will run through the city of Lima and will have an approximated length of 62 km and secondary ducts will have an initial length of 23 km. In order to build the main duct it has been divided in three sections: South, Center and North.

Up to April 2004, the main progress of this project is the following:

In July 2002 the Environmental Impact Assessment of Natural Gas Distribution by Pipeline Network in Lima and Callao was approved.

In December 2002 the last pipe load of 20” arrived, completing the pipes to be used in the main duct and the secondary branches.

In October, construction works of the South Section of the Main Duct began.

Up to April 30, 2004, the total progress of the main duct installation of Distribution systems is of 96%, with the following detail:

  • Topographic Survey 84.20 km
  • Pipe Stringing 82.60 km
  • Trenching 82.30 0 km
  • Welding 82.40 km
  • Lowering-in and back filling 82.29 km
  • Restoration 82.13 km

During April 2004 continued works in the following fronts of the Main Pipeline: City Gate (Lurin), Terminal Station (Ventanilla) and Vinsa branch line. Also, Citygate works continued with a 99% progress.

In April 2004 finished works for hydraulic tests of fourth and last section of the trunk line. Also, works for hydraulic tests of branch lines and entrance spool for initial clients continued.

Up to April 30, 2003 , total progress of the project, including Engineering and Supplies is of 98.20 %.

  back to top...
space.gif (43 bytes)
space.gif (43 bytes)
space.gif (43 bytes)
All Rights Reserved Perupetro S.A. © 2010
space.gif (43 bytes)
space.gif (43 bytes)